Accotink Pump Station and Freund House Pump Station Electrical

Cynergy performed a $2,572,533 contract for Fairfax County Dept. of Public Works for the replacement of 5KV service switchgear at two pumping stations. The engineer of record was Hazen and Sawyer; John Harmon, PE. The project was awarded in March 2015 and completed almost one year ahead of schedule. Major elements of work at both pumping stations included demolition of existing switchgear and associated electrical equipment, conduits and wire and furnishing and installing new Dominion Virginia Power approved 5KV service switchgear, associated electrical equipment, conduits and wire.  The contract also included site work, underground duct-banks, paving, surfacing, fencing, grading, landscaping, erosion and sedimentation control, precast concrete, handrails and painting.

 